May 23, 2015
You’re driveway is in and first round of painting is done.
May 20, 2015
Painting has begun!!
May 15, 2015
Drywall is almost finished!!
May 5, 2015
And drywall is just about complete!
May 2, 2015
Dry wall has started! The boys are hard at work!
April 29, 2015
More insulation and wiring is done!
April 24, 2015
The wiring is finished and windows and doors are being installed!
April 21, 2015
Wiring, insulation, siding, and doors and windows are on the docket for this week.
April 17, 2015
Happy Friday!! You now have a roof and can see the layout of your home.
April 14, 2015
The foundation is in and framing has begun!!
March 30, 2015
And with that the ground is broken
March 12, 2015
We have made it on the big board! Our anticipated “ground break week” is 3/30, we will also be having our pre- construction meeting that same week
January 18, 2015
Congratulations on the purchase of your new Eastwood home! I am very excited to begin this journey with you.
As we move through the process I will be documenting and updating you with this web page that you can share with all of your friends and family.