January 27, 2018
This 1930’s Tudor Bungalow Is A Sans Souci Show Stopper. Rehabbed With The Past In Mind, Encaustic Art Tile & The Original Pine & Oak Floors Continue This Home’s Retro Profile. New Kitchen, Bathroom, Roof & Electrical. This Character Filled Home Includes A Partially Unfinished Laundry Basement, Backyard Dog Park & Stainless Steel Appliances. (Even The Refrigerator) Location- 3 Miles From Downtown Greenville.
January 27, 2018
January 23, 2018
House is shaping up and almost ready for staging.
January 20, 2018
Floors are complete, finishing touches happening next week.
January 16, 2018
Floor Stain Is Selected
January 14, 2018
Tiling is complete. Appliances have been delivered. We are now sanding the original hardwoods!
January 13, 2018
Day 15 | Kitchen tile is down and the bathroom is in the works! Front door is painted!
January 12, 2018
Tile Going In, still a couple adjustments to make on backsplash ( delete back wall tile) Nearing the finish line.
January 8, 2018
Day 10 | Last bit of cosmetic touch-ups. The tile has arrived and we will begin installing tomorrow!
January 4, 2018
Day 7 | Kitchen is coming to life! Recessed lights have been installed, bathroom shower is ready for tile, and the brick has arrived on site.
January 1, 2018
We’re back from our New Years break! All new electrical wiring is complete and Interior paint finished.
December 28, 2017
Day 3 | Interior and Exterior trim has been painted. All new electric wiring has begun!
December 27, 2017
Day 2 | Sidewalk completed, cabinet and countertop install, interior trim painting begins
December 26, 2017
Day 1| New Sidewalk Added & Rear Fence Moved
December 26, 2017
day 1 | New Roof, bathroom Demo, kitchen demo & cabinet install.
December 26, 2017
Before